Review Agenda Item
Meeting Date: 5/23/2024 - 6:15 PM
Category: APPROVAL OF CONSENT AGENDA
Type: Action
Subject: For action - High School Center II Design Development Phase
ACPS Division Objective :
Goal 3
Equitable, Transformative Resources
Policy: FA - Building and Naming Facilities
Enclosure
File Attachment:
HS Center II Design Development.pdf
Summary: Albemarle County Public Schools is designing a new high school center on the Lambs Lane Campus. High School Center II is planned to serve 400 students per day at a size of approximately 60,000 SF. The project will also comply with School Board policy FEBCA. The schematic design was approved by the School Board on January 25, 2024. The Design Committee has continued to further refine the plans to align with Division goals, which has included significant input from students, teachers, families, and other key stakeholders.
Funding: The funds for A/E Professional Services were included in the FY24 Capital Improvements Program. Construction funding is included in FY25.
Recommendation: It is recommended that the design development documents are received and staff is authorized to proceed to the Construction Documents and Bidding phases. This item was reviewed for information on May 9, 2024.
Approvals:
Recommended By:
Signed By:
Matt Wertman - Director of Building Services
Signed By:
Rosalyn Schmitt - Chief Operating Officer
Signed By:
Dr. Matthew Haas - Superintendent